Attachment A
Major Works and Refurbishment Communities
57 communities to receive housing refurbishments
Tara Gunyangara Imangara Belyuen Kybrook Farm Yuelamu Eva Valley Finke Acacia Larrakia Titjikala Weemol Wutunugurra Amanbidji Yarralin Rittarangu Mutitjulu Wallace Rockhole Pmara Jutunta Nturiya Nyirripi Wilora Minjilang Bulla Willowra Haasts Bluff Mount Liebig Canteen Creek Laramba Robinson River Jikminggan Imanpa Barunga Bulman Amoonguna Engawala Papunya Atitjere Pirlangimpi Pigeon Hole Alpurrurulam Peppimenarti Kaltukatjara Areyonga Nganmarriyanga Binjari Milikapiti Santa Teresa Warruwi Ramingining Nauiyu Daguragu Beswick Kalkarindji Minyerri Kintore Ampilatwatja Ali Curung
16 communities to receive major capital works
Hermannsburg Gunbalanya Yirrkala Nguiu Gapuwiyak Galiwinku Numbulwar Maningrida Angurugu Wadeye Umbakumba Lajamanu Milyakburra Milingimbi
[ top ]
Attachment B
Alliance Partners and their members
Earth Connect Alliance
- Canstruct Pty Ltd
- WorleyParsons Services Pty Ltd
- Force 10 International Pty Ltd
- Greene & Associates Pty Ltd
- Ostwald Bros. Pty Ltd
Territory Alliance Partners are
- Sitzler Pty Ltd
- Laing O'Rourke Australia Construction Pty Ltd
- McMahon Services Australia Pty Ltd
With a Sub Alliance Participant
- Compass Group (Australia) Pty Ltd
New Future Alliance
- Leighton Pty Ltd
- Broad Construction Services Pty Ltd
- Opus Pty Ltd
- Ngarda Civil & Mining Pty Ltd
[ top ]
Attachment C
SIHIP Communities Map

[ top ]
Attachment D
Construction Activity 2004-2009
New Community Houses Constructed in Northern Territory Remote Indigenous Communities between 2004-05 and 2008-09
| |
2004-05 |
2005-06 |
2006-07 |
2007-08* |
2008-09* |
| Number of new houses |
94 |
51 |
64 |
102 |
66 |
| Cumulative number of new houses |
94 |
145 |
209 |
311 |
377 |
*Between December 2007 and June 2009 102 new houses were built.
[ top ]
Attachment E
Revised Program Budget
| SIHIP element |
Target |
Average unit cost |
Total |
| New houses |
750 |
$450, 000 |
$337, 500, 000 |
| Rebuilds |
230 |
$200, 000 |
$46, 000, 000 |
| Refurbishments |
2, 500 |
$ 75, 000 |
$187, 500, 000 |
| Project Management |
8 percent of program |
|
$53, 760 000 |
| Contingency* |
|
|
$47, 240 000 |
| Total |
|
|
$672, 000, 000 |
* Contingency is a normal allocation in a capital project and covers eventualities such as cost escalation on materials and labour and major stoppages or problems due to litigation, weather etc. In the event that contingencies are not required they will be used for capital works.